Worked example: 180 kW Norfolk free-range egg unit — multi-shed install
Project at a glance
- System size
- 180 kW across two free-range egg sheds
- Annual generation
- 172,000 kWh
- Annual saving
- £39,500
- Simple payback
- 5.6 yr
Modelled worked example. The figures below are modelled from typical 2026 UK costs, yields and tariffs for this building type and system size — this is an illustrative scenario, not a named client project.
Scenario: Free-range egg producer (350,000 hens) Location: North Norfolk Vertical: Poultry Sheds System size: 180 kW across two free-range egg sheds Annual generation: 172,000 kWh Annual saving: £39,500 Simple payback: 5.6 years
A North Norfolk free-range egg producer running 350,000 laying hens across two clear-span insulated sheds, each 80m × 22m with high year-round ventilation and lighting loads. Annual electricity spend before install: £58,000. Operating under RSPCA Assured and Lion Quality scheme membership, with major UK retailer supply contracts that increasingly reference Scope 2 supplier disclosure.
180 kW rooftop PV installed across both sheds — 330 modules in total, two string inverters per shed, all wired to the central control building’s main switchboard. An install like this runs under full Avian Influenza biosecurity protocols (boot dips, restricted access lanes, cleaning station, all-team daily decontamination) in a six-week window between flock changeovers.
The modelled system achieves 78% self-consumption thanks to continuous ventilation and lighting baseload across both sheds, generating around 172,000 kWh a year. The remainder exports under SEG, modelled at 12p/kWh (the top of the flat-tariff range as at July 2026).
Modelled annual savings of roughly £39,500 in year one across cost avoidance and export income. Simple payback at 5.6 years; 100% AIA tax relief applied year one against the farming partnership’s trading profit. For producers on retailer contracts, a documented install of this kind feeds directly into Scope 2 supplier disclosure — increasingly material at contract review.
Other case studies
Worked example: 120 kW Cotswolds mixed farm — workshop and grain store
120 kW across workshop and grain store • 6.7-yr payback
Worked example: 320 kW Cheshire dairy farm — combined re-roof and PV
320 kW • 5.2-yr payback
Worked example: 240 kW Shropshire pig finisher unit — high baseload
240 kW across three finisher houses • 5.8-yr payback