G99 Grid Connection for Farm Solar via National Grid Electricity Distribution (NGED, formerly Western Power)

How NGED handles farm-building solar G99 connections in 2026. Timelines, capacity context, no-export workarounds.

  • Independent guidance

What NGED covers

National Grid Electricity Distribution (NGED, formerly Western Power) is the Distribution Network Operator responsible for Midlands, South West, South Wales. The network covers the rural farming areas across West Midlands, East Midlands, Gloucestershire, Wiltshire, Dorset, Somerset, Devon, Cornwall, Herefordshire, Worcestershire, plus Pembrokeshire/Carmarthenshire (South Wales). In these areas any array above 16 A per phase (3.68 kW single-phase or 11.04 kW three-phase) needs a G99 application approved by NGED before it is energised; below that, G98 connect-and-notify applies (ENA Engineering Recommendations G98 and G99).

Which inverter goes on the application form, and whether it can be export-limited if the acceptance comes back capped, is covered on solar inverters for farm buildings.

The G99 application process via NGED

The NGED G99 application is submitted via their connections portal (https://www.nationalgrid.co.uk/customers/connections). Standard timeline:

  • Application submission: within 14 days of contract signature (your installer submits immediately after the structural survey)

Current capacity context across NGED's network

South Devon, Cornwall, and parts of West Midlands have ongoing reinforcement programmes; Midland heartland generally available. For farms on capacity-constrained feeders, the rational design path is "no-export" — sizing the PV system for 100% self-consumption with zero grid export.

NGED-specific G99 requirements

NGED requires standard G99 documentation: system specification (panel and inverter make and model, total kW capacity); single-line electrical diagram; grid-code compliance certificate (inverter manufacturer certification); structural compliance confirmation; site address and grid reference; existing supply details (MPAN, contracted kVA, phase configuration). For installs above 250 kW, NGED typically requires additional fault-level study and harmonic distortion analysis.

Connection charges to expect on NGED's network

Indicative NGED connection charges for typical farm PV installs in 2026:

    For projects where the NGED quote is uneconomic, the options to ask an installer about are: reducing system capacity to fit within existing feeder limits; no-export design eliminating export reinforcement; battery storage to absorb peak generation; staged commissioning where Phase 1 connects under existing capacity.

    How to minimise NGED G99 timeline impact on your project

    Three actions consistently shorten the G99 timeline:

    1. Submit early. A good installer submits the G99 application within 14 days of contract signature, before detailed electrical design completes. The application can be updated as design firms up; what matters is being in the NGED queue.
    2. Pre-engage NGED where possible. For larger installs (above 500 kW), informal pre-application discussions with the NGED connections team can flag capacity constraints before formal submission, allowing design adjustments.

    Working with NGED on combined re-roof + PV projects

    For projects involving asbestos cement removal followed by PV installation, the G99 application is submitted at the same time as the asbestos removal contractor mobilises. Both workstreams run in parallel through the re-clad and into commissioning. NGED does not require coordination with the asbestos contractor — the G99 process is electrical-only.

    Who does what on a NGED G99 application

    This site is independent guidance, not an installer, and does not prepare or submit G99 applications. On most farm projects the installer drafts the application from the structural and electrical design, submits it through the NGED portal, answers the network operator's technical queries and arranges the final connection. Ask each installer to confirm in writing who does each step, and what happens to the price and programme if the study comes back with reinforcement costs.

    Common questions

    How long does NGED take to approve a G99 connection?

    The distribution network operator (DNO) is the company that owns the local network, set by the site’s location rather than the electricity supplier. It sets its own G99 study timescales and any reinforcement cost, so ask it for current figures in writing before relying on a programme; the process is covered in the guide to DNO grid connection for rural farm solar.

    What's the G99 connection cost on NGED's network?

    There is no single price for an install of this kind. The official DESNZ series for 2025/26 gives a mean installed cost of £1,266.84 per kW for 10–50 kW systems (£1,167.29 for non-domestic installations in that band), but it covers MCS installations up to 50 kW across all building types, so larger farm systems are priced from written quotes. The farm solar cost guide sets out the series and what moves a farm quote.

    Can we connect a farm PV system on a capacity-constrained NGED feeder?

    Yes — using no-export design. The PV system is sized for 100% self-consumption with zero grid export.

    Does NGED have special requirements for large farm installs?

    For installs above 250 kW, NGED typically requires additional fault-level study and harmonic distortion analysis. Above 1 MW, full grid-code compliance documentation. Ask each installer whether these studies are in their price.

    When should we submit the G99 application to NGED?

    The distribution network operator (DNO) is the company that owns the local network, set by the site’s location rather than the electricity supplier. It sets its own G99 study timescales and any reinforcement cost, so ask it for current figures in writing before relying on a programme; the process is covered in the guide to DNO grid connection for rural farm solar.

    Independent, data-led farm solar guidance

    • Independent specialist guidance
    • Sourced 2026 rates & grant data — last reviewed July 2026