What is different for a farm building in Northern Ireland
Northern Ireland has its own planning order and its own grid. NIE Networks is regulated by the Utility Regulator, not Ofgem. There is no Smart Export Guarantee, the rates rules differ, and DAERA runs farm support. Only the tax reliefs are shared with Great Britain. This page covers those differences for barns, sheds, dairy units and grain stores.
Planning: Part 37, not the English Class J
Rooftop solar on a non-domestic building falls under Part 37 Class A of the Planning (General Permitted Development) Order (Northern Ireland) 2015. Its conditions:
- panels no more than 20 cm beyond the plane of the roof slope;
- on a flat roof, no more than 2 m above the highest part of the roof and not within 2 m of its edge;
- not beyond the edge of the roof or wall, and not above the ridge;
- in a conservation area or World Heritage Site, not on a road-facing visible roof slope;
- within the curtilage of a listed building, listed building consent is needed.
A stand-alone array falls under Class B: no more than 2 m high, at least 5 m from the curtilage boundary and no more than 30 m². Anything larger needs planning permission. Read the order's own text for your building rather than a summary.
Grid: NIE Networks, G98/NI and G99/NI
NIE Networks is the sole distribution network operator, and SONI operates the transmission system. Up to 16 A per phase (3.68 kW single-phase or 11.04 kW three-phase) a system connects under G98/NI. The installer submits the commissioning form within 30 days, though several installs on one site need a network study first.
Since 1 May 2026 the G99/NI Fast Track covers systems up to 60 A per phase installed with export capped at 16 A per phase. It still needs approval before installation, as full G99/NI does: under full G99/NI you have 90 days to accept an offer. Most farm-building arrays are in G99/NI territory, so apply early. NIE's generation capacity map was upgraded on 9 March 2026, and the GB connection-queue reforms do not apply in Northern Ireland.
Export: no Smart Export Guarantee
The Smart Export Guarantee covers installations in Great Britain only. In Northern Ireland the export rate is set by each supplier. Power NI publishes a micro-generation export tariff of 11.88p per kWh for 1 October 2026 to 30 September 2027, reviewed annually; check which system sizes it covers and what other suppliers offer. Exports have been settled on actual meter reads since 1 October 2022. The Northern Ireland Renewables Obligation closed to new generation in 2017. Wind and solar dispatch-down was 22% in 2025, so a farm roof sized for its own daytime use usually works better than one sized for export.
Yield on a Northern Ireland shed roof
| Point (PVGIS) | 10° south (kWh/kWp) | Optimal tilt (kWh/kWp) |
|---|---|---|
| Belfast | 828 | 922 |
| Enniskillen | 779 | 854 |
| Derry/Londonderry | 769 | 843 |
Rates
Generating plant up to 50 kW is not rateable under the Rates (Microgeneration) Order (Northern Ireland) 2012. Above 50 kW it is rateable, and plant that mainly serves the property is valued with the host building. The 2026 revaluation was halted on 29 January 2026, with no new date.
Funding in Northern Ireland: what is open and what is not
- DAERA Sustainable Farming Investment Scheme: Round 1 closed. It paid 40% of a reference price. Its item list of 10 July 2026 had no rooftop or ground-mounted solar PV, batteries or heat pumps, only items such as milk plate coolers, heat recovery, variable-speed vacuum pumps and small solar water pumps and fence energisers. Further rounds are expected, with no dates.
- NISEP business grant: closed for 2026/27. Power NI's NISEP-funded grant for business solar PV (20%, capped at £30,000) has closed for applications for 2026/27; Power NI expects the next round to open in April 2027, subject to funding approval.
- Invest NI Energy Efficiency Capital Grant: paused. It is not accepting enquiries or applications and has no reopening date. Its 2024 guidance excluded farms in any case.
- Non-Domestic RHI: closing out. Closed to new applicants since 2016; Ofgem's administration ends on 30 November 2026.
- Tax: UK-wide. 100% Annual Investment Allowance on the PV plant (special-rate), then the 50% special-rate first-year allowance. A farm business building pays 20% VAT, reclaimable if VAT-registered. The 0% rate for energy-saving materials on homes, such as the farmhouse, began in Northern Ireland on 1 May 2023 and runs to 31 March 2027.
Realistic expectation: no grant pays for solar on a Northern Ireland farm-building roof today. The routes are self-funding against the allowances, finance or a power purchase agreement, compared on the grants and funding guide.
Solar in Northern Ireland in numbers
Installed solar PV in Northern Ireland rose from 6 MW in 2012 to 371 MW in 2024, across 32,342 sites, and renewables supplied 50% of electricity consumption in the year to June 2026 (Department for the Economy).
Sources
Each figure above was checked against these primary sources on 3 November 2026. Schemes and tariffs change, so read the current page before you rely on one.
- Planning (General Permitted Development) Order (NI) 2015, Part 37
- NIE Networks: G98/NI microgeneration limits
- NIE Networks: G99/NI applications
- NIE Networks: capacity map upgrade (March 2026)
- Ofgem: Smart Export Guarantee (Great Britain only)
- Power NI: micro-generation tariff rates
- PVGIS (European Commission Joint Research Centre)
- Department of Finance: renewable energy valuation practice notes
- DAERA: Sustainable Farming Investment Scheme
- Utility Regulator: NISEP list of schemes 2026/27
- Invest NI: Energy Efficiency Capital Grant
- Department for the Economy: Energy in Northern Ireland 2026
Common questions
Do I need planning permission for solar on a farm building in Northern Ireland?
Often not for a roof array. Part 37 Class A of the Northern Ireland permitted development order allows rooftop solar on a non-domestic building if the panels sit no more than 20 cm beyond the roof slope (on a flat roof, no more than 2 m above the highest part and not within 2 m of the edge), stay within the roof edge and below the ridge, and avoid road-facing slopes in conservation areas. A listed curtilage needs listed building consent, and a stand-alone array above 30 m² needs planning permission.
Does the Smart Export Guarantee apply in Northern Ireland?
No. The Smart Export Guarantee covers Great Britain only. In Northern Ireland each supplier sets its own export rate; Power NI publishes a micro-generation export tariff of 11.88p per kWh for 1 October 2026 to 30 September 2027.
Is there a grant for solar panels on farm buildings in Northern Ireland?
Not at the moment. DAERA's Sustainable Farming Investment Scheme Round 1 is closed and did not list rooftop solar or batteries. Power NI's NISEP-funded grant for business solar PV (20%, capped at £30,000) has closed for applications for 2026/27, with the next round expected to open in April 2027, subject to funding approval. The Invest NI Energy Efficiency Capital Grant is paused.
Do I need NIE Networks' approval before installing?
For most farm-building arrays, yes. Systems up to 16 A per phase connect under G98/NI with a commissioning form within 30 days. Anything larger needs G99/NI approval before installation, including the Fast Track route available since 1 May 2026 for systems up to 60 A per phase with export capped at 16 A per phase.