G99 Grid Connection for Farm Solar via Scottish and Southern Electricity Networks (SSEN)

How SSEN handles farm-building solar G99 connections in 2026. Timelines, capacity context, no-export workarounds.

  • Independent guidance

What SSEN covers

Scottish and Southern Electricity Networks (SSEN) is the Distribution Network Operator responsible for Southern England, North Scotland, Highlands and Islands. The network covers the rural farming areas across Hampshire (north), Berkshire, Oxfordshire, Buckinghamshire (south), Wiltshire (east), Aberdeenshire, Highland, Perthshire, Argyll and Bute, Western Isles. In these areas any array above 16 A per phase (3.68 kW single-phase or 11.04 kW three-phase) needs a G99 application approved by SSEN before it is energised; below that, G98 connect-and-notify applies (ENA Engineering Recommendations G98 and G99).

The G99 application process via SSEN

The SSEN G99 application is submitted via their connections portal (https://www.ssen.co.uk/connections/). Standard timeline:

  • Application submission: within 14 days of contract signature (your installer submits immediately after the structural survey)

Current capacity context across SSEN's network

Highland feeders frequently closed to new export; Berkshire and Oxfordshire generally available. For farms on capacity-constrained feeders, the rational design path is "no-export" — sizing the PV system for 100% self-consumption with zero grid export.

SSEN-specific G99 requirements

SSEN requires standard G99 documentation: system specification (panel and inverter make and model, total kW capacity); single-line electrical diagram; grid-code compliance certificate (inverter manufacturer certification); structural compliance confirmation; site address and grid reference; existing supply details (MPAN, contracted kVA, phase configuration). For installs above 250 kW, SSEN typically requires additional fault-level study and harmonic distortion analysis.

Connection charges to expect on SSEN's network

Indicative SSEN connection charges for typical farm PV installs in 2026:

    For projects where the SSEN quote is uneconomic, the options to ask an installer about are: reducing system capacity to fit within existing feeder limits; no-export design eliminating export reinforcement; battery storage to absorb peak generation; staged commissioning where Phase 1 connects under existing capacity.

    How to minimise SSEN G99 timeline impact on your project

    Three actions consistently shorten the G99 timeline:

    1. Submit early. A good installer submits the G99 application within 14 days of contract signature, before detailed electrical design completes. The application can be updated as design firms up; what matters is being in the SSEN queue.
    2. Pre-engage SSEN where possible. For larger installs (above 500 kW), informal pre-application discussions with the SSEN connections team can flag capacity constraints before formal submission, allowing design adjustments.

    Working with SSEN on combined re-roof + PV projects

    For projects involving asbestos cement removal followed by PV installation, the G99 application is submitted at the same time as the asbestos removal contractor mobilises. Both workstreams run in parallel through the re-clad and into commissioning. SSEN does not require coordination with the asbestos contractor — the G99 process is electrical-only.

    Who does what on a SSEN G99 application

    This site is independent guidance, not an installer, and does not prepare or submit G99 applications. On most farm projects the installer drafts the application from the structural and electrical design, submits it through the SSEN portal, answers the network operator's technical queries and arranges the final connection. Ask each installer to confirm in writing who does each step, and what happens to the price and programme if the study comes back with reinforcement costs.

    Common questions

    How long does SSEN take to approve a G99 connection?

    The distribution network operator (DNO) is the company that owns the local network, set by the site’s location rather than the electricity supplier. It sets its own G99 study timescales and any reinforcement cost, so ask it for current figures in writing before relying on a programme; the process is covered in the guide to DNO grid connection for rural farm solar.

    What's the G99 connection cost on SSEN's network?

    There is no single price for an install of this kind. The official DESNZ series for 2025/26 gives a mean installed cost of £1,266.84 per kW for 10–50 kW systems (£1,167.29 for non-domestic installations in that band), but it covers MCS installations up to 50 kW across all building types, so larger farm systems are priced from written quotes. The farm solar cost guide sets out the series and what moves a farm quote.

    Can we connect a farm PV system on a capacity-constrained SSEN feeder?

    Yes — using no-export design. The PV system is sized for 100% self-consumption with zero grid export.

    Does SSEN have special requirements for large farm installs?

    For installs above 250 kW, SSEN typically requires additional fault-level study and harmonic distortion analysis. Above 1 MW, full grid-code compliance documentation. Ask each installer whether these studies are in their price.

    When should we submit the G99 application to SSEN?

    The distribution network operator (DNO) is the company that owns the local network, set by the site’s location rather than the electricity supplier. It sets its own G99 study timescales and any reinforcement cost, so ask it for current figures in writing before relying on a programme; the process is covered in the guide to DNO grid connection for rural farm solar.

    Independent, data-led farm solar guidance

    • Independent specialist guidance
    • Sourced 2026 rates & grant data — last reviewed July 2026